Dismantling and removal of old 132kV GIS
Minor Civil works modifications for Installation of the new GIS
Installation, Testing and commissioning of new 132kV GIS with Local Control Cubicles
Installation and commissioning of new cable Sealing Ends between existing 132kVcables and new GIS
Connecting the new installed GIS with another existing GIS and energizing as one system
Modification, installation and testing works for the new and old control protection system.
Project Details:
Client: ABB Switzerland Ltd
End User: Ministry of Electricity – Iraq
Year: 2015
location: Nasriya – Iraq