Construction, Installation, and Related Services for the 132/33 kV GIS Imam Sadek Grid Substation (TPIF Unit 3.2)
132/33 kV GIS Imam Sadek Grid Substation Project located within GGIP-Ratawi Solar TPIF project.With MITAS Energy and Metal Construction

132/33 kV GIS Imam Sadek Grid Substation Project located within GGIP-Ratawi Solar TPIF project.With MITAS Energy and Metal Construction

Rehabilitation works for the bus-duct related to the 400kV Al-Hartha line bay, at Qurna 400 Substation, in addition to the replacement works for the damaged equipment, and the required commissioning works for the bay.

132kV Cables pulling, testing and termination works. The works were done at NCS2 site for BGC,

Installation works for 132kV outdoor “Cable sealing end” with JGC Corperation.

Installation works for 36 no. of HV 132 kV cable terminations, using prysmian termination kits in addition to the HV testing works.

installation of (6 no.) of outdoor terminations (Prysmian type) and (6 no.) of indoor termination (Pfisterer type). in addition to the HV testing works for the installed cables and terminations.

The Installation, Testing & Commissioning Works for 132 & 33kV GIS and HV Cables in addition to Power Transformer oil filling and treatment.

Our Scope includes Construction works including Civil, Installation, and Testing & Commissioning Works for Establishment of Al Hussainiya 132kV Substation.

Engineering consultation, design, Supply, Install, Test. commission, and energize the new 132kV GIS system equipment including the consultation for the design of the new civil works to suit the rehabilitation works.

Our scope includes the completion of all the ETC works & HV testing for 6 (Six) numbers of 132/33kV Substations in this project.